Namibia: KORYX COPPER’S HAIB PRE-FEASIBILITY STUDY SHOWS US$2.5 BILLION (N$43 BILLION) POST-TAX NPV FOR A 24-YEAR, 48MTPA COPPER MINE IN SOUTHERN NAMIBIA

The study, which backs a US$2.06 billion (N$34.9 billion) build and a maiden Probable reserve of 3 million tonnes of contained copper, puts Haib among the largest copper developments in Namibia, though the company still has to complete a feasibility study, raise finance and secure permits.

Koryx Copper S.A. has released a pre-feasibility study (PFS) for its wholly owned Haib Copper Project in southern Namibia. The study shows a post-tax net present value at an 8% discount rate (NPV8%) of US$2.5 billion, or N$43 billion (US$4.2 billion or N$71 billion pre-tax). The post-tax internal rate of return is 24.9% (30.6% pre-tax), with a post-tax payback of 3.9 years.

Those results assume flat long-term prices of US$5.00 a pound for copper (N$85), US$3,500 an ounce for gold and US$22 a pound for molybdenum. At a copper price of US$13,000 a tonne (about US$5.90 a pound), post-tax NPV rises to US$3.9 billion (N$65.6 billion), the IRR to 32.2% and payback shortens to 3.5 years. The cash flow model is unlevered, on a 100% project basis, and includes no streaming or offtake prepayment.

Haib is a large, disseminated porphyry copper deposit with molybdenum and gold by-products, planned as a conventional open pit with sulphide milling and flotation. The project sits about six kilometres north of the South African border in the Karas Region, 12 to 15 kilometres east of the B1 highway.

In the first 10 years, the mine is forecast to produce an average of 135,000 tonnes of copper a year in concentrate, or 130,000 tonnes of payable copper. Gross copper-equivalent output averages 145,000 tonnes a year over that period. Over the full 24-year life, Haib is expected to produce 2.61 million tonnes of copper in concentrate, averaging 109,000 tonnes a year (105,000 tonnes payable).

First 10 yearsLife of mine
Copper in concentrate (ktpa)135109
Payable copper (ktpa)130105
Payable gold (oz a year)15,00012,000
Payable molybdenum (million lb a year)1.221.13
C1 cash cost per lbUS$1.72 (N$29.12)US$2.19 (N$37.08)
All-in sustaining cost per lbUS$2.07 (N$35.05)US$2.52 (N$42.66)
Capital intensity (per tonne of annual payable CuEq)US$14,985 (N$253,700)US$18,584 (N$314,600)

The company expects about 95% of life-of-mine gross revenue to come from copper, 3% from gold and 2% from molybdenum.

Upfront capital is US$2.06 billion (N$34.9 billion), including US$133 million (N$2.3 billion) of project contingency and US$152 million (N$2.6 billion) of capitalised pre-stripping. Sustaining capital totals US$639 million (N$10.8 billion) over the life of the mine. Construction is assumed to take two years, with capital spent 40% in the first year and 60% in the second.

The model assumes a 3% government royalty and a 1% export levy. Corporate income tax is 37.5%, an effective rate of 32% of pre-tax profit over the mine’s life. Total tax paid is estimated at US$4.3 billion (N$72.6 billion).

Mining will be done by a contractor using electric rope shovels and 360-tonne diesel-electric trucks, with trolley assist on designated haul routes. The pit will be developed in five pushbacks, targeting higher-grade feed early. Mining runs for 15 years after pre-stripping, at a life-of-mine strip ratio of 0.98 to 1. Lower-grade ore will be stockpiled and processed once mining ends. In the final two years, about 61 million tonnes of oxide and transitional stockpiles will be treated.

The plant is sized for 48 million tonnes a year and uses three-stage crushing with high-pressure grinding rolls, ball milling, and coarse particle flotation that rejects 25% of run-of-mine feed as barren coarse tailings. It then uses a hybrid of Jameson cells and tank cells, targeting 89.5% copper recovery in the first 10 years (87.3% over the life of the mine) and a concentrate grading 21.8% copper. Molybdenum and gold are recovered as by-products. The study drops the heap leach facility included in the company’s September 2025 preliminary economic assessment (PEA).

The Mineral Resource, effective 28 October 2026, totals 4.35 million tonnes of contained copper. It comprises 1,371 million tonnes of Indicated resource at 0.26% copper and 329 million tonnes of Inferred resource at 0.24% copper, reported at a 0.15% cut-off.

The maiden Mineral Reserve, effective 6 November 2026, is classed entirely as Probable. It stands at 1,119 million tonnes grading 0.27% copper, containing about 2.995 million tonnes of copper, 65,000 tonnes of molybdenum and 689,000 ounces of gold. Only Indicated resources were converted to reserves, and Inferred material was treated as waste in the mine plan.

The mine’s peak demand is estimated at 261 MVA, with annual consumption of about 1,650 GWh. Supply will come from a 220kV connection to NamPower’s Harib substation, combined with about 417 MWp of on-site solar PV and 361 MWh of battery storage, supplying about 45% of life-of-mine energy. Namibia’s Electricity Control Board has granted Koryx contestable-customer status for up to 49.9% of the project’s power needs, subject to a Power Supply Agreement with NamPower.

Water of about 20 million cubic metres a year will be drawn from the Orange River, with an off-channel storage dam to manage seasonal flows. Koryx has a signed memorandum of understanding with NamWater and has applied for a 33-year abstraction licence. The tailings facility, selected from nine alternatives, will hold about 1.15 billion tonnes.

Koryx also plans a township near Noordoewer on about 36.6 hectares, with 370 erven for around 2,000 residents. The company intends to provide 543 housing units.

Koryx said the next 12 months will focus on completing a definitive feasibility study (DFS), raising finance and finishing permitting. The DFS is due to start in early 2027 and take about a year, and the company plans a strategic options and project financing review during 2027. It aims to have its Mining Licence and Environmental Clearance Certificate by mid-2027, begin early works late in 2027 and start construction in the first quarter of 2028.

Two of four expected Environmental Clearance Certificate applications have been lodged, for the mine in August 2026 and for water abstraction and supply in September 2026. The applications for the Grunau railway siding and bulk power infrastructure are expected by mid-2027.

Chief executive Heye Daun said the results “far exceeded our initial expectations” and described Haib as “a truly world-class copper development project in a premium jurisdiction, Namibia”. He said the main improvements over the PEA were a larger, higher-grade resource, a maiden reserve, the removal of heap leaching, coarse particle flotation and Jameson cell technology, and flowsheet optimisation.

The study identifies a number of risks. They include recovery uncertainty at lower feed grades because of tailings assay variance, a preliminary gold recovery model, unconfirmed copper recovery from oxide and transitional material in the final two years, and water-recovery risk from the tailings facility as it grows. Town planning and land-use approvals are long-lead items with no fixed timelines. A PFS also carries a lower level of confidence than a feasibility study.

Environmental studies follow International Finance Corporation standards, and public meetings were held in Windhoek, Keetmanshoop, Karasburg and Noordoewer. Koryx said stakeholder perception is generally positive, with interest in jobs and community development, and key concerns around water availability and population influx.

Koryx will hold an investor webcast on Wednesday 18 November and a site visit and investor day on 4 and 5 February 2027.

Presentation & Investor Webinar

Koryx management will host a live webinar conference call to discuss the results of the PFS.

Live, online webinar conference call to discuss PFS results:

Date: Wednesday, November 18th, 2026

Time: 10:00 am EST, 17:00 Namibia time

Webcast Registration Link: https://bit.ly/4zJJw3z

Related posts

Atlas Copco Compressor Technique blows profit into the Low Pressure market

Staff

Secure supply, efficiency needed for mining growth

Staff

ZAMBIAN GOVERNMENT WELCOMES STRENGTHENED MINING SECTOR COOPERATION WITH FRENCH GOVERNMENT

Staff

Leave a Comment