# Zimbabwe: ZIMBABWEAN EXPERTISE SHINES IN MIMOSA TAILINGS DAM CONSTRUCTION

- Link: https://miningconstruction-sadc.com/zimbabwe-zimbabwean-expertise-shines-in-mimosa-tailings-dam-construction/
- Published: 2025-02-27T17:26:16+02:00
- Author: Staff

The construction of the large TSF-4 tailings storage facility at Mimosa platinum
mine – the second largest TSF in Zimbabwe – has demonstrated the ingenuity of local
firms, working in close collaboration with SRK Consulting.

The Mimosa Mining Company, owned by Sibanye-Stillwater and Implats, had appointed
SRK Consulting (South Africa) to conduct the detailed design of TSF4 – and this 
was completed in May 2022. The next part of the contract – lasting about two years
up to March 2024 – covered the civils works and the electrical infrastructure and
instrumentation to operate the facility. According to SRK partner and principal 
civil engineer Andrew Robertshaw, SRK was also involved in oversight of the project
implementation, its quality and its scheduling.

“This was a sizeable project that has resulted in a technologically advanced TSF
structure measuring some 1 km by 1,3 km,” said Robertshaw. “The storage capacity
of the facility is substantial, based on a production rate of 466,000 tonnes per
month over a 20-year deposition period.”

**Empowerment**

Key to the client’s strategy was the involvement and empowerment of local companies;
among the main players in the construction and related duties were Harare-based 
Forit Contracting and local laboratory services company Kumba Resources Zimbabwe.
Paterson & Cooke Consulting Engineers were engaged for the mechanical and electrical
design.

Designed and built to comply with the Global Industry Standard on Tailings Management(
GISTM), published in 2020, the TSF-4 also had to deal with specific local conditions
such as a high level of talc in the tailings. This material stays in suspension 
for lengthy periods, requiring a longer time to settle.

“There are further challenges when the material does settle, as the fine material
can cover and block the drains under the TSF,” he explained. “This could lead to
water forcing its way out of the dam through other routes, such as under its foundations
or through its walls, creating a serious structural risk.”

**Complex drainage**

Working with Robertshaw was SRK corporate consultant Robert McNeil, who said that
the drainage system design had to be complex and cutting-edge to deal with the challenge
of the talc content.

“It was important for us to remove the water in the tailings as quickly as possible,
via a robust drainage system through the dam foundations at ground level,” said 
McNeil. “As the water drains, a series of conduits collect the water and channel
it down to one of lowest topographical points.”

An in-line pump station pumps the water around the eastern side of the structure
and into a silt-trap dam where remaining suspended solids have more residence time
to settle out before the water continues to the return water dam.

“A great deal of work went into understanding the seepage on this facility, and 
how we decant water from the structure,” he said. “We also wanted to include ‘future-
proofing’ elements in the design, which would, at little extra cost, extend the 
operational life of the facility.”

**Drainage components**

The TSF has been provided with a complex network of drains, designed to ensure drainage
of the TSF outer shell, and a means to monitor the efficiency of the desaturation
at many locations.

Internal paddocks have been designed to run alongside the inside walls of the TSF.
The purpose of the paddocks is to provide smaller areas for deposition, allowing
the settlement of the coarser fraction of tailings and the creation of a well-drained
outer shell. The paddocks fill quickly with coarse tailings, while the finer tailings
and talc, with a longer settlement time, flow over the inner paddock walls into 
the main basin – where the finer tailings and talc settle. Forcing the fine material
away from the main drain reduces the opportunity for talc to settle over and clog
the main drain.

The main drains are strategically placed vertically below the crest of the full 
level. This allows the operator to build the TSF to the initial 30 m height, or 
to extend the TSF life to a full development height of 60 m. These main drains aid
drawdown of the outer shell’s phreatic surface to reduce the risk of failure.

The paddocks are an important element of McNeil’s commissioning plan, which allows
early deposition of tailings while keeping the talc material away from the critical
main drains. He pointed out that, as part of the application of best practice, the
TSF was not only clay-lined but there was also extensive use of high-density polyethylene
lining in the drains.

“Within the footprint of the dam itself, all the drains are lined with HDPE as well,”
said McNeil. “Using both the clay lining – including a four-metre layer of clay 
on the walls – and the HDPE represented quite a unique approach. This was the optimal
response to both the geochemistry and the very flat gradients at the site.”

Robertshaw noted that the interface between TSF-4 and an existing TSF also required
a specific solution to potential seepage, comprising a complex array of pipework
to monitor and understand where water flows were emanating.

**Penstocks**

Impala’s philosophy to duplicate critical infrastructure was reflected in the choice
to provide two penstock towers and pipelines discharging separately into the two-
compartment silt trap. This duplication both allows one component to be taken out
of commission to enable cleaning of the associated silt trap compartment, and to
provide redundancy should one system become inoperable. The towers have been designed
with three outlet heights which, when combined with the ringing up method, allow
decanting all the way to 60 m.

**Local laboratory**

The on-site laboratory, established by Kumba Resources Zimbabwe with technical guidance
from SRK, was important for talking samples of various materials and delivering 
quick results to allow the project to proceed expeditiously. This was a key component
of quality assurance on the site, he said. Typically, the contractor would run their
own laboratory and consultants would need to check if these results were accurate.
The Kumba laboratory team numbered almost a dozen, including specialist samplers
and testing technicians, who worked 24-7 in three shifts towards the end of the 
project to complete the necessary work in time.

“One of the joys of this project was the dedication, expertise and attention to 
detail exhibited by the lab team,” said Robertshaw. “With our regular visits and
collaboration, we were able to facilitate considerable upskilling of the team.”

The lab now has a solid track record of providing on-site quality assurance to a
large TSF development – testing earthworks materials and concrete, and keeping detailed
records over the span of the project.

A similar developmental approach was taken with the role of Forit Contracting in
this project, with the mine and SRK working with the contractor to ensure the necessary
resources were available and better utilised. The early site clearing was undertaken
manually, but as the project gathered momentum, Forit was able to increase its earthmoving
plant fleet on site to around 150 items at the peak.

SRK’s construction specialists were on hand to advise on various aspects of plant
scheduling and availability, to ensure the contract was kept on track while meeting
all required specifications. SRK provided the project with a highly experienced 
scheduler who reviewed and updated progress on a weekly basis. A local safety, health
and environment (SHE) practitioner was appointed to oversee project safety.

“The developmental approach led to a real sense of achievement among all involved,
showing how the local economic impact of a project can be enhanced as part of a 
strategic commitment to responsible mining,” said Robertshaw.

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/zimbabwe-zimbabwean-expertise-shines-in-mimosa-tailings-dam-construction/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/zimbabwe-zimbabwean-expertise-shines-in-mimosa-tailings-dam-construction/?share=x)

### Like this:

Like Loading…

### _Related_