# Zimbabwe: PREMIER AFRICAN MINERALS RAISES £1.2M TO RESTART ZULU LITHIUM PLANT, BUT FUNDING COVERS ONLY A 15-DAY TEST RUN

- Link: https://miningconstruction-sadc.com/zimbabwe-premier-african-minerals-raises-1-2m-to-restart-zulu-lithium-plant-but-funding-covers-only-a-15-day-test-run/
- Published: 2026-10-06T13:19:36+02:00
- Author: Staff

_**AIM-listed miner issues 27.5 billion new shares at 0.00436p, diluting existing
holders by about 35.5%, as it pivots from stockpile-building to a short campaign
to prove the Zimbabwe plant can run stably**_

Premier African Minerals has raised about £1.2 million to restart processing at 
its Zulu Lithium and Tantalum Project in Zimbabwe. The money will initially fund
only a 15-day operating campaign, designed to show whether the plant can deliver
stable production.

The AIM-listed company said on October 5 that it had issued 27.52 billion new shares
at 0.00436 pence each to institutional and professional investors. The net proceeds
will provide working capital for the planned recommencement of operations at Zulu.

The restart marks a shift from Premier’s earlier strategy, which was to build a 
larger run-of-mine (ROM) stockpile before switching the processing plant back on.

Managing Director Graham Hill said the funding “enables us to move directly towards
restarting plant operations at Zulu”, adding that the decision was “a change from
our original plan, which was to build a larger ROM stockpile before recommencing
processing.”

Hill said progress during the previous operating period had given the board enough
confidence to go ahead using material already on site. “However, the progress achieved
during the previous operating period has provided the Board with a basis to proceed
with the restart, while maintaining our focus on achieving stable and consistent
production of spodumene concentrate,” he said.

Premier plans to process about 13,000 tonnes of ore already on the ROM pad over 
a campaign of roughly 15 days. The campaign will be judged on four measures: sustained
plant operation, product quality, recoveries and throughput.

“We believe the best use of the Company’s available resources at this stage is to
process the material already on the ROM pad and demonstrate the satisfactory performance
of the plant,” Hill said. “Our immediate target is an approximately 15-day campaign,
during which the principal focus will be on sustained plant operation, product quality
and recoveries.”

The company said the results will determine whether operations continue beyond the
initial test. Premier is not presenting the £1.2 million as enough for a full-scale
restart. The cash is being used to establish whether the plant can operate consistently
before further capital is committed.

Personnel, diesel, reagents and other consumables are being mobilised, and supplier
engineers are expected on site to support operations and further optimise the spodumene
flotation plant.

Additional blasted ore remains available within Zulu’s exploration prospecting area(
EPO). It could be moved to the ROM pad after the initial campaign, but only if the
plant performs satisfactorily and enough working capital is available.

“Importantly, this approach should provide us with the opportunity to extend operations,”
Hill said. He added that “additional blasted material remains available within the
EPO and may be mobilised to the ROM pad following the initial campaign, subject 
to satisfactory performance and the availability of working capital.”

Premier said the results would feed into its next decisions. They will “inform subsequent
operational and funding decisions, including the potential remobilisation of mining
activities and continuation of plant operations beyond the initial 15-day period.”

Zulu therefore faces a two-stage test. It must first prove the existing ore can 
be processed reliably, then secure enough funding to keep the plant supplied and
move back towards mining and sustained production.

Hill said the operational evidence would also matter in talks with investors. “A
successful campaign should provide the Board, shareholders and potential funding
partners with greater visibility on the operational capability of Zulu and a stronger
basis from which to determine the next stage of the project,” he said.

The placing substantially enlarges Premier’s share count. The company has issued
27,522,935,780 new shares, taking total issued share capital to 77,597,203,602. 
The new shares represent about 35.5% of the enlarged capital, so existing shareholders
who did not take part in the subscription face significant dilution.

Premier said the proceeds will principally fund operating expenditure at Zulu, including
mining and stockpiling, operational personnel, diesel, reagents and other consumables.
They will also cover “the management of essential creditors at Zulu” and the group’s
wider working capital needs.

The raise comes as Premier tries to move Zulu from repeated operational and financing
difficulties towards consistent production. The company has previously stressed 
the importance of stable operations at the project, and this announcement puts plant
performance ahead of rebuilding a larger stockpile. The approach also lets Premier
use the 13,000 tonnes already on the pad as an operational test, rather than committing
scarce cash to a bigger stockpile before the plant has shown it can perform.

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/zimbabwe-premier-african-minerals-raises-1-2m-to-restart-zulu-lithium-plant-but-funding-covers-only-a-15-day-test-run/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/zimbabwe-premier-african-minerals-raises-1-2m-to-restart-zulu-lithium-plant-but-funding-covers-only-a-15-day-test-run/?share=x)

### Like this:

Like Loading…

### _Related_