# Zambia: ZCCM-IH COMMENCES MANGANESE MINING OPERATIONS IN SERENJE

- Link: https://miningconstruction-sadc.com/zambia-zccm-ih-commences-manganese-mining-operations-in-serenje/
- Published: 2020-05-06T10:54:07+02:00
- Author: Staff

Works at the manganese mine in Serenje have commenced following the end of the heavy
rains that had hampered kick-starting operations, posing a challenge in accessing
the mine site areas.

ZCCM Investments Holdings Plc (ZCCM-IH) through its wholly owned subsidiary Kabundi
Resources Limited (KRL) are on site and have started Phase one of the project in
the small-scale mining license, with an initial capital injection of K18.6 million.

Phase two of the project which is scheduled to start before the onset of this year’s
rainy season will be extended to other areas of the ZCCM-IH Large Scale Exploration
area in Serenje.

ZCCM-IH Chief Executive Officer Mr. Mabvuto Chipata undertook a site visit end of
April 2020, were he also inspected works at the Kampumbu Resettlement area earmarked
for relocation of nine (9) households from the Kabundi mine site.

The Resettlement Action Plan (RAP) approved by the Zambia Environmental Management
Services (ZEMA) involves the construction of an additional one-by-two classroom 
block, a health center, nine-by-three bedroomed houses for the relocation of the
Project Affected families, one house for a teacher, and another house for a medical
staff.

These buildings will also be serviced and fully connected with piped water sourced
from water boreholes to be drilled in the area.
 Mr. Chipata was happy with the 
progress made both at the mining operation and the RAP sites. He stated that the
mine will be fully operational by July 2020, and looked forward to having it officially
launched by August 2020.

ZCCM-IH will spend a total of K4.5 million to fulfil the RAP obligations, which 
are scheduled to be handed over to the beneficiaries in June 2020.

The RAP project has so far employed over 20 locals. KRL will further employ over
150 youths at the mine site as production scales up upon relocation of the affected
families.
 KRL targets to mine about 60,000 tonnes of manganese by the end of the
year during the ramp up period of operations.

Production is targeted to reach 240,000 tonnes of manganese ore annually once commercial
production is achieved.
 The Company is a strategic investment aimed at diversifying
the commodity mix of the ZCCM-IH’s portfolio which is largely comprised of copper
producing assets.

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/zambia-zccm-ih-commences-manganese-mining-operations-in-serenje/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/zambia-zccm-ih-commences-manganese-mining-operations-in-serenje/?share=x)

### Like this:

Like Loading…

### _Related_