Tailings facility owners are facing the challenge of how to practically integrate
social impacts with the systems that manage tailings – as required by the Global
Industry Standard for Tailings Management (GISTM). Global engineers and scientists
[SRK Consulting](http://www.srk.co.za) has proposed a four-step process to achieve
this.

The steps cover four key aspects: knowledge sharing, training and awareness; a critical
review of systems for gaps and opportunities; upgrading of data systems to highlight
targets and trigger action; and strategies for ongoing collaboration and development.

“The importance of social aspects in the GISTM is quite clear,” said [SRK Consulting](http://www.srk.co.za)
principal environmental consultant Jacky Burke. “It appears as the very first topic
in the 2020 publication of the standard, where mines are required to ‘meaningfully
engage project-affected people at all phases of the tailings storage facility (TSF)
lifecycle’.”

For a start, meaningful engagement requires a range of formalised systems, procedures
and monitoring with reference in the GISTM to the mine’s Environmental and Social
Management System (ESMS). However, Burke noted that a key hurdle is the typical 
separation of the more ‘technical’ tailings systems from environmental, social and
governance (ESG) systems on most mining sites.

“Mines will generally have an ESMS that operationalises several of the ESG requirements
of the GISTM, while there is also a Tailings Management System (TMS) that gives 
effect to both engineering and governance considerations of the GISTM,” she said.“
The current challenge is to integrate the ESMS with the TMS in a way that is practical
and effective.”

**Integrating social and environmental**

that need to be integrated with the TMS – the environmental and social components
are themselves often not adequately integrated within the mining operation. They
are usually managed as separate entities, and often within different departments.
While environmental issues may fall under the Safety, Health and Environment (SHE)
Department, social management may fall under a Community Engagement or Social Performance
Department.

“There are, of course, many different disciplines and skill-sets involved in each
function – and each team has its own day-to-day responsibilities and imperatives,”
Burke said. “Conformance to the GISTM will require stronger interaction and integration
between the range of disciplines and various systems dealing with engineering, social
and environmental monitoring, risk management and change management.”

Driving this integration is the growing urgency on the compliance front, as International
Council on Mining and Metals (ICMM) members are working towards a conformance deadline
little over a year away. Mines which operate their TSFs with very high or extreme
potential consequence ratings must comply with the GISTM by August 2023.

**Mind-shift**

Key to the essential ‘mind-shift’ which is embodied in the GISTM requirements is
to elevate social engagement from being intermittent to being ongoing. Focused engagement
is often associated with permitting, as part of the regulatory public participation
process during environmental authorisation processes and water use licensing applications.

Engagements with affected people should therefore be focused, meaningful and ongoing
during the life of the operation and throughout the lifecycle of a TSF – with integration
into the regular routines of tailings and environmental management. There is already
a greater focus on the importance of environmental and social scientists alongside
their engineering colleagues, said Franciska Lake, partner and principal environmental
scientist at [SRK Consulting](http://www.srk.co.za). This trend is a positive factor
that will facilitate alignment with the GISTM requirements at an operational level.

**Informed by risk**

This integration of environmental, social and engineering imperatives must, according
to the GISTM, be informed by the identified risks. Further, the standard calls for
a performance-based monitoring system and governance framework that encompasses 
both the ESMS and TMS and requires regular review and audit of these systems.

“As the cross-cutting demands of the GISTM may present challenges, the four-step
process provides a framework in which mines can structure and evaluate their progress,”
said Lake “Importantly, the steps need to be applied iteratively throughout the 
life of the tailings facility; adaptation will be ongoing supporting effective implementation
of the GISTM.”

The first proposed step is concerned with knowledge sharing, training and awareness
of a mine’s environmental, social and tailings management teams. The aim is to build
mutual understanding among the respective experts on their roles and functions within
the site-specific context of their operation and the risks that these pose.

**Finding opportunities**

“It is therefore critical that this first step involves tailings engineers and operators
in collaboration with environment and social management personnel – to facilitate
the integration process,” said Lake. “This collaborative group needs to share how
site-specific risks are currently being dealt with by the ESMS and TMS, and find
opportunities to engage affected people on identified tailings facilities.”

The second step of the process lays the groundwork for the mines to comply with 
the GISTM requirements through reviews and internal audits. It conducts a critical
review of the ESMS and TMS, looks at specific areas for improvement and integration,
and identifies gaps in its conformance with the GISTM.

**Assess and report**

This underpins the third step, where data management systems can be upgraded to 
facilitate integrated assessment and reporting. The system will set performance 
targets, and trigger action if these are not met. Along with specifying responsible
people for each variable being monitored, the system would also need to include 
reporting frameworks and schedules in line with what the GISTM requires.

“The fourth step in the process is ongoing collaboration and development, which 
could involve regular meetings of a forum of GISTM disciplines on the mine,” said
Burke. “This forum shares lessons learnt, and keeps everyone informed of risks and
corrective actions.”

Lake acknowledged that applying the four-step approach demanded considerable effort
and commitment by mine personnel, especially being an iterative process where adaptation
and adjustment would always be required. With the GISTM firmly embraced by the sector,
and with investors and regulators alike watching its implementation closely, it 
is vital that mines invest the necessary resources and time to ensure conformance
to the GISTM.

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/south-africa-building-social-engagement-into-tailings-management/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/south-africa-building-social-engagement-into-tailings-management/?share=x)

### Like this:

Like Loading…

### _Related_