Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers of
titanium minerals and zircon, which operates the Moma Titanium Minerals Mine in 
northern Mozambique, is pleased to provide an update following the relocation of
Wet Concentrator Plant (“WCP”) B, to Pilivili, in late October 2020.

**Statement from Michael Carvill, Managing Director:**

_“The ramp-up of WCP B is progressing well, having been operating for more than 
a month, and production is in line with expectations. The temporary measures we 
implemented to mitigate project delays, caused by global COVID-19 restrictions, 
have been effective. We expect operations at Pilivili to be running on grid power
before the end of the year, while the Heavy Mineral Concentrate pumping system is
to begin commissioning in Q1 2021._

_It’s been encouraging to see that spot prices for ilmenite, our primary product,
have increased strongly in Q4, after a marginal softening in Q3. Higher production
and lower unit costs, coupled with a robust commodity market, will help to support
higher capital returns for shareholders from 2021.”_

WCP B has experienced a smooth ramp-up in Pilivili, following the previously announced
commencement of production in late October 2020. Production has been in line with
expectations and ore grades have been significantly higher than the grades previously
being mined in Namalope, as anticipated. The temporary measures put in place to 
allow mining to commence have been operating successfully. These involved powering
WCP B with diesel-powered electric generators and trucking Heavy Mineral Concentrate(“
HMC”) from Pilivili to the Mineral Separation Plant (“MSP”).

With installation of the powerline completed in mid-November 2020 and the installation
of the electrical substations anticipated to be completed shortly, operations at
Pilivili are expected to be grid powered from mid-December 2020.

Kenmare is on track to begin the commissioning and ramp-up of the HMC pumping system
during Q1 2021. The pumps have been installed on the infrastructure terrace and 
the final parts of the pipeline are expected to be delivered to site in late January
2021.

The MSP has previously achieved a monthly run-rate of 1.2 million tonnes of ilmenite
per annum on a short-term basis, but Kenmare’s focus is now on operating at this
targeted run-rate consistently. In recent years operations have been constrained
by HMC production volumes, but with increased HMC production, supported by the move
to Pilivili and the commencement of production from WCP C in February 2020, a greater
emphasis is being placed on operational resilience. During H2 2020, additional separation
capacity has been installed at the ilmenite circuits, while construction of a 25%
increase in product storage is also underway.

The ilmenite product market has been robust in Q4 2020, supported by strong pigment
demand and lower ilmenite production, particularly in China. These markets dynamics
are supportive of Kenmare’s plans to increase supply in 2021, helping to meet global
demand.

For further information, please contact:
    **Kenmare Resources plc**Jeremy Dibb/
Katharine SuttonInvestor RelationsTel: +353 1 671 0411Mob: + 353 87 943 0367 / +
353 87 663 0875

**Murray (PR advisor)**
Joe HeronTel: +353 1 498 0300Mob: +353 87 690 9735

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/mozambique-update-on-mining-operations-at-pilivili/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/mozambique-update-on-mining-operations-at-pilivili/?share=x)

### Like this:

Like Loading…

### _Related_