# B2Gold Reports Strong Gold Production for Q1 2022 with Total Gold Production of 209,365 oz, 5% Above Budget; On Track to Meet Annual Guidance of 990,000 to 1,050,000 oz of Total Gold Production.

- Link: https://miningconstruction-sadc.com/b2gold-reports-strong-gold-production-for-q1-2022-with-total-gold-production-of-209365-oz-5-above-budget-on-track-to-meet-annual-guidance-of-990000-to-1050000-oz-of-total-gold-production/
- Published: 2022-04-14T09:54:59+02:00
- Author: Staff

B2Gold Corp. (TSX: BTO) (NYSE AMERICAN: BTG) (NSX: B2G) (“B2Gold” or the “Company”)
is pleased to announce its gold production and gold revenue for the first quarter
of 2022. All dollar figures are in United States dollars unless otherwise indicated.**
2022 First Quarter Highlights**

 * Total gold production of 209,365 ounces (including 12,892 ounces of attributable
   production from Calibre Mining Corp. (“Calibre”)), 5% (9,760 ounces) above budget,
   and consolidated gold production of 196,473 ounces from the Company’s three operating
   mines, 4% (8,431 ounces) above budget, with solid performances from all the Company’s
   three mines, with each mine exceeding its budgeted production for the first quarter
   of 2022
 * Consolidated gold revenue was $366 million on sales of 195,100 ounces at an average
   realized price of $1,874 per ounce
 * For 2022, B2Gold remains well positioned for continued strong operational and
   financial performance with total gold production guidance of between 990,000 –
   1,050,000 ounces (including 40,000 – 50,000 attributable ounces projected from
   Calibre) with total consolidated cash operating costs forecast to be between 
   $620 – $660 per ounce _(see “Non-IFRS Measures”) _and total consolidated all-
   in sustaining costs (“AISC”)_ (see “Non-IFRS Measures”)_ forecast to be between
   $1,010 – $1,050 per ounce
 * The Company announced an updated and significantly increased Mineral Resource
   estimate for the Anaconda area, comprised of the Menankoto permit and the Bantako
   North permit, located approximately 20 kilometres from the Fekola Mine; preliminary
   planning by the Company has demonstrated that a pit situated on the Anaconda 
   area could provide saprolite (weathered) material to be trucked to and fed into
   the Fekola mill commencing as early as late 2022, subject to obtaining all necessary
   permits and completion of a final mine plan, with the potential to add an average
   of approximately 80,000 to 100,000 ounces per year to the Fekola mill’s annual
   gold production
 * B2Gold’s Namibian subsidiary was recognized by the Namibian Revenue Agency as
   the highest revenue contributor among “Overall Top Contributors” in calendar 
   year 2021

**Gold Production**

Total gold production in the first quarter of 2022 was 209,365 ounces (including
12,892 ounces of attributable production from Calibre), above budget by 5% (9,760
ounces), and consolidated gold production from the Company’s three operating mines
was 196,473 ounces, above budget by 4% (8,431 ounces), with solid performances from
the Company’s three mines, with each mine exceeding its budgeted production for 
the first quarter of 2022 (see “Operations” section below). Due to the timing of
higher-grade ore mining, consolidated gold production from the Company’s three operating
mines is expected to be significantly weighted to the second half of 2022. As expected,
compared to the first quarter of 2021, total consolidated gold production was lower
by 5% (11,279 ounces), due to the planned significant waste stripping campaign and
lower mined ore tonnage at the Fekola Mine in the first quarter of 2022, as Phase
6 of the Fekola Pit continues to be developed in the first half of 2022. 

The Company is currently compiling its consolidated cash operating costs and consolidated
AISC results for the first quarter of 2022, which will be released along with its
first quarter of 2022 financial results after the North American markets close on
Tuesday, May 3, 2022.

For full-year 2022, the Company’s total gold production is forecast to be between
990,000 – 1,050,000 ounces (including 40,000 – 50,000 attributable ounces projected
from Calibre) with total consolidated cash operating costs forecast to be between
$620 – $660 per ounce and total consolidated AISC forecast to be between $1,010 –
$1,050 per ounce. The Company’s consolidated gold production from its three operating
mines is forecast to be between 950,000 – 1,000,000 ounces in 2022, with consolidated
cash operating costs forecast to be between $600 – $640 per ounce and consolidated
AISC forecast to be between $1,000 – $1,040 per ounce. Notwithstanding the ongoing
sanctions on Mali announced by the Economic Community of West African States (“ECOWAS”)
on January 9, 2022, including closure of a number of the borders with Mali, the 
Fekola Mine continues to operate at full capacity and the Company expects to meet
its 2022 production guidance for the Fekola Mine.

For the first half of 2022, consolidated gold production is forecast to be between
390,000 – 410,000 ounces, which is expected to increase significantly to between
560,000 – 590,000 ounces during the second half of 2022. Based mainly on the weighting
of production and timing of stripping activities, consolidated cash operating costs
are expected to be between $760 – $800 per ounce in the first half of 2022, before
significantly improving to between $490 – $530 per ounce during the second half 
of 2022. In addition, consolidated AISC are expected to be between $1,250 – $1,290
per ounce in the first half of 2022 before significantly improving to between $820–
$860 per ounce during the second half of 2022.**Gold Revenue  **

For the first quarter of 2022, consolidated gold revenue was $366 million on sales
of 195,100 ounces at an average realized price of $1,874 per ounce, compared to 
$362 million on sales of 202,330 ounces at an average realized price of $1,791 per
ounce in the first quarter of 2021. The slight increase in gold revenue of 1% ($
4 million) was 5% attributable to the increase in the average realized gold price,
offset by a 4% impact from the decrease in gold ounces sold (mainly due to the lower
gold production).  **Operations**

Mine-by-mine gold production in the first quarter of 2022 (including the Company’s
estimated 25% attributable share of Calibre’s production) was as follows:  

| **Mine** | **Q1 2022****Gold Production****(ounces)** | **First-Half 2022****Forecast****Gold Production****(ounces)** | **Second-Half 2022 Forecast****Gold Production****(ounces)** | **Full-year 2022 Forecast****Gold Production****(ounces)** | 
| Fekola | 101,648 | 220,000 – 230,000 | 350,000 – 370,000 | 570,000 – 600,000 | 
| Masbate | 59,764 | 105,000 – 110,000 | 100,000 – 105,000 | 205,000 – 215,000 | 
| Otjikoto | 35,061 | 65,000 – 70,000 | 110,000 – 115,000 | 175,000 – 185,000 | 
| **_B2Gold Consolidated ^((1))_** | **196,473** | **390,000 –410,000** | **560,000 – 590,000** | **950,000 – 1,000,000** | 
|  |  |  |  |  | 
| **_Equity interest in Calibre ^((2))_** | **12,892** | **20,000 – 25,000** | **20,000 – 25,000** | **40,000 – 50,000** | 
|  |  |  |  |  | 
| **Total** | **209,365** | **410,000 – 435,000** | **580,000 – 615,000** | **990,000 – 1,050,000** |

| _(1)_ | _“B2Gold Consolidated” – gold production is presented on a 100% basis, as B2Gold fully consolidates the results of its Fekola, Masbate and Otjikoto mines in its consolidated financial statements (even though it does not own 100% of these operations).   _ | 
| _(2)_ | _“Equity interest in Calibre” – represents the Company’s approximate 25% indirect share of Calibre’s operations. B2Gold applies the equity method of accounting for its 25% ownership interest in Calibre. _ |

Fekola Gold Mine – Mali

The Fekola Mine in Mali had a successful start to the year with first quarter of
2022 gold production of 101,648 ounces, slightly above budget by 1% (917 ounces),
as higher than budgeted processed grade (6%) offset lower than budgeted processed
tonnes (5%). Following initial difficulties with importing reagents into Mali as
a result of economic border sanctions imposed on Mali by ECOWAS, on January 9, 2022,
as a precautionary response, the planned processing of saprolite ore at the Fekola
Mine was temporarily suspended to reduce reagent consumption and ensure that sufficient
reagents remained available to process higher-grade ore to meet budgeted gold production(
which resulted in lower than budgeted throughput for the first quarter of 2022).
Although the sanctions continue, the situation has normalized as regular imports
of reagents were received by Fekola in February and March 2022. As a result, saprolite
ore was reintroduced back into the Fekola mill feed blend at the end of February
2022, and the processing of saprolite ore resumed as planned. Fekola’s gold production
is expected to be significantly weighted to the second half of 2022 when mining 
reaches the higher-grade portion of Phase 6 of the Fekola Pit and Cardinal operations
are at full capacity. As expected, compared to the first quarter of 2021, Fekola’s
gold production was lower by 19% (23,440 ounces), due to planned significant waste
stripping and lower mined ore tonnage, as Phase 6 of the Fekola Pit continues to
be developed in the first half of 2022.

For the first quarter of 2022, mill feed grade was 1.54 grams per tonne (“g/t”) 
compared to budget of 1.45 g/t and 1.99 g/t in the first quarter of 2021; mill throughput
was 2.20 million tonnes compared to budget of 2.31 million tonnes and 2.07 million
tonnes in the first quarter of 2021; and gold recovery averaged 93.3% compared to
budget of 93.5% and 94.4% in the first quarter of 2021. For the first quarter of
2022, as described above, processed grade was above budget while processed tonnes
were below budget mainly due to the temporary suspension of processing saprolite
ore, offset by the processing of higher-grade ore, in January and February 2022.
Processed grade was lower compared to the first quarter of 2021 due to the planned
significant waste stripping campaign in the first quarter of 2022.  

The Fekola Mine is expected to produce between 570,000 – 600,000 ounces of gold 
in 2022 at cash operating costs of between $510 – $550 per ounce and AISC of between
$840 – $880 per ounce. For the first half of 2022, Fekola’s gold production is expected
to be between 220,000 – 230,000 ounces, which is expected to increase significantly
to between 350,000 – 370,000 ounces during the second half of 2022. Based mainly
on the weighting of production and timing of pre-stripping, Fekola’s cash operating
costs are expected to be between $720 – $760 per ounce in the first half of 2022,
before significantly improving to between $380 – $420 per ounce during the second
half of 2022. In addition, Fekola’s AISC are expected to be between $1,140 – $1,180
per ounce in the first half of 2022, before significantly improving to between $
660 – $700 per ounce during the second half of 2022.

_Anaconda Area_

On March 23, 2022, the Company announced an updated and significantly increased 
Mineral Resource estimate for the Anaconda area, comprised of the Menankoto permit
and the Bantako North permit, located approximately 20 kilometres from the Fekola
Mine. The updated and significantly increased Anaconda Mineral Resource estimate(
as at January 11, 2022) constrained within a conceptual pit shell at a gold price
of $1,800 per ounce included an initial Indicated Mineral Resource estimate of 32,400,000
tonnes at 1.08 g/t gold for a total 1,130,000 ounces of gold, and Inferred Mineral
Resource estimate of 63,700,000 tonnes at 1.12 g/t gold for 2,280,000 ounces of 
gold. The Mineral Resource estimate included first time reporting of 1,130,000 ounces
of Indicated Mineral Resources and an increase of 1,510,000 ounces (196% increase)
of Inferred Mineral Resources since the initial Inferred Mineral Resource estimate
in 2017 (21,590,000 tonnes at 1.11 g/t gold, for 767,000 ounces).

In 2022, the Company has budgeted $33 million for development of infrastructure 
for Phase I saprolite mining at the Anaconda area, including road construction. 
Based on the updated Mineral Resource estimate and B2Gold’s preliminary planning,
the Company has demonstrated that a pit situated on the Anaconda area could provide
selective higher grade saprolite material (average grade of 2.2 g/t) to be trucked
to and fed into the Fekola mill commencing as early as late 2022 at a rate of 1.5
million tonnes per annum. Subject to obtaining all necessary permits and completion
of a final development plan, the trucking of selective higher grade saprolite material
to the Fekola mill would increase the ore processed and annual gold production from
the Fekola mill, with the potential to add an average of approximately 80,000 to
100,000 ounces per year to the Fekola mill’s annual gold production. The plan to
truck the selective higher grade saprolite material is not included in the Company’s
2022 production guidance and the Anaconda area Mineral Resources have not been included
in the current Fekola life of mine plan.

Based on this updated Mineral Resource Estimate and the 2022 exploration drilling
results, the Company has commenced a Phase II scoping study to review the project
economics of constructing a stand-alone mill near the Anaconda area. Subject to 
receipt of a positive Phase II scoping study, the Company expects that the saprolite
material would continue to be trucked to and fed into the Fekola mill during the
construction period for the Anaconda area stand-alone mill.

In 2022, the Company will continue drilling to infill and extend the saprolite resource
area and to follow up on the sulphide mineralization at the Anaconda area, including
the Mamba and Adder zones, and several other targets below the saprolite mineralization.
The good grade and width combinations at the Anaconda area continue to provide a
strong indication of the potential for Fekola-style south plunging bodies of sulphide
mineralization, which remains open down plunge. Five drill rigs are currently drilling
in the Anaconda area.

Masbate Gold Mine – The Philippines

The Masbate Mine in the Philippines had a strong start to the year with first quarter
of 2022 gold production of 59,764 ounces, above budget by 11% (5,711 ounces) and
4% (2,251 ounces) higher compared to the first quarter of 2021, mainly due to higher
processed grade.  

For the first quarter of 2022, mill feed grade was 1.19 g/t compared to budget of
1.09 g/t and 1.10 g/t in the first quarter of 2021; mill throughput was 2.01 million
tonnes compared to budget of 1.93 million tonnes and 1.95 million tonnes in the 
first quarter of 2021; and gold recovery averaged 78.0% compared to budget of 79.7%
and 83.6% in the first quarter of 2021. Processed grade was above budget in the 
first quarter of 2022 due to mining additional (unbudgeted) higher-grade areas identified
within the planned mining areas. In addition, mine haulage optimizations (which 
resulted in shorter than planned hauls of waste and increased mining rates) also
contributed to the above budgeted mined high-grade ore tonnage in the first quarter
of 2022. Compared to the first quarter of 2021, gold recoveries were lower as a 
result of processing a higher proportion of fresh rock ore in the first quarter 
of 2022.    

The Masbate Mine is expected to produce between 205,000 – 215,000 ounces of gold
in 2022 at cash operating costs of between $740 – $780 per ounce and AISC of between
$1,070 – $1,110 per ounce. Masbate’s gold production is scheduled to be relatively
consistent throughout 2022.

Otjikoto Gold Mine – Namibia

The Otjikoto Mine in Namibia performed well during the first quarter of 2022, producing
35,061 ounces of gold, 5% (1,803 ounces) above budget, with processed tonnes, grade
and recoveries all slightly better than budget. As a result of the timing of higher-
grade ore mining, Otjikoto’s gold production is expected to be significantly weighted
to the second half of 2022 when mining is scheduled to reach the higher-grade portions
of Phase 3 of the Otjikoto Pit and ore production ramps up at the Wolfshag underground
mine. As expected, compared to the first quarter of 2021, gold production was significantly
higher by 52% (12,019 ounces), as processed ore in the first quarter of 2021 was
primarily sourced from existing stockpiles while significant waste stripping operations
continued at both the Wolfshag and Otjikoto pits.

For the first quarter of 2022, mill feed grade was 1.31 g/t compared to budget of
1.26 g/t and 0.82 g/t in the first quarter of 2021; mill throughput was 0.85 million
tonnes compared to budget of 0.84 million tonnes and 0.89 million tonnes in the 
first quarter of 2021; and gold recovery averaged 98.5% compared to budget of 98.0%
and 97.6% in the first quarter of 2021.

Development of the Wolfshag underground mine continues to progress with ore production
expected to commence in the first half of 2022. The initial underground Mineral 
Reserve estimate for the down-plunge extension of the Wolfshag deposit includes 
210,000 ounces of gold in 1.2 million tonnes of ore at 5.57 g/t gold.

The Otjikoto Mine is expected to produce between 175,000 – 185,000 ounces of gold
in 2022 at cash operating costs of between $740 – $780 per ounce and AISC of between
$1,120 – $1,160 per ounce. For the first half of 2022, Otjikoto’s gold production
is expected to be between 65,000 – 70,000 ounces, which is expected to increase 
significantly to between 110,000 – 115,000 ounces during the second half of 2022.
Based mainly on the weighting of the planned production and timing of pre-stripping,
Otjikoto’s cash operating costs are expected to be between $960 – $1,000 per ounce
in the first half of 2022, before significantly improving to between $620 – $660
per ounce during the second half of 2022. In addition, Otjikoto’s AISC are expected
to be between $1,460 – $1,500 per ounce in the first half of 2022, before significantly
improving to between $930 – $970 per ounce during the second half of 2022.**Outlook**

The Company is pleased with its first quarter of 2022 production results as outlined
in this news release, particularly given the challenges mining companies are facing
around the world. Based on a strong first quarter, the Company is on track to meet
its annual gold production guidance for 2022 of  between 990,000 – 1,050,000 ounces(
including 40,000 – 50,000 attributable ounces projected from Calibre) with total
consolidated cash operating costs of between $620 – $660 per ounce and total consolidated
AISC of between $1,010 – $1,050 per ounce. The Company is currently compiling its
consolidated cash operating costs and consolidated AISC results for the first quarter
of 2022, which will be released along with its first quarter of 2022 financial results
after the North American markets close on Tuesday, May 3, 2022.

The Company’s ongoing strategy is to continue to maximize profitable production 
from its mines, further advance the Anaconda and Gramalote development projects,
advance the Company’s numerous brownfield and greenfield exploration projects, evaluate
new exploration, development and production opportunities and continue to pay an
industry leading dividend yield.**First Quarter 2022 Financial Results – Conference
Call Details**

B2Gold will release its first quarter of 2022 financial results after the North 
American markets close on Tuesday, May 3, 2022.

B2Gold executives will host a conference call to discuss the results on Wednesday,
May 4, 2022, at 10:00 am PST/1:00 pm EST. You may access the call by dialing the
operator at +1 (778) 383-7413 / +1 (416) 764-8659 (Vancouver/Toronto) or toll free
at +1 (888) 664-6392 prior to the scheduled start time or you may listen to the 
call via webcast by clicking [here](https://c212.net/c/link/?t=0&l=en&o=3505411-1&h=529968270&u=https%3A%2F%2Fwww.webcaster4.com%2FWebcast%2FPage%2F1493%2F45262&a=here).
A playback version will be available for two weeks after the call at +1 (416) 764-
8677 (local or international) or toll free at +1 (888) 390-0541 (passcode 666652#).**
Qualified Persons**

Bill Lytle, Senior Vice President and Chief Operating Officer, a qualified person
under NI 43-101, has approved the scientific and technical information related to
operations matters contained in this news release.

**ON BEHALF OF B2GOLD CORP.**

**“Clive T. Johnson” President and Chief Executive Officer

For more information on B2Gold please visit the Company website at [www.b2gold.com](https://c212.net/c/link/?t=0&l=en&o=3505411-1&h=3283032929&u=http%3A%2F%2Fwww.b2gold.com%2F&a=www.b2gold.com)
or contact:

| Randall Chatwin | Katie Bromley | 
| Senior Vice President, Legal & | Manager, Investor Relations &   | 
| Corporate Communications | Public Relations | 
| 604-681-8371 | 604-681-8371  | 
| [rchatwin@b2gold.com](https://miningconstruction-sadc.com/b2gold-reports-strong-gold-production-for-q1-2022-with-total-gold-production-of-209365-oz-5-above-budget-on-track-to-meet-annual-guidance-of-990000-to-1050000-oz-of-total-gold-production/rchatwin@b2gold.com) | [kbromley@b2gold.com](https://miningconstruction-sadc.com/b2gold-reports-strong-gold-production-for-q1-2022-with-total-gold-production-of-209365-oz-5-above-budget-on-track-to-meet-annual-guidance-of-990000-to-1050000-oz-of-total-gold-production/kbromley@b2gold.com) |

First Name

Last Name

Email

I agree to the privacy policy and terms.

### Share this:

 * [  Facebook ](https://miningconstruction-sadc.com/b2gold-reports-strong-gold-production-for-q1-2022-with-total-gold-production-of-209365-oz-5-above-budget-on-track-to-meet-annual-guidance-of-990000-to-1050000-oz-of-total-gold-production/?share=facebook)
 * [  X ](https://miningconstruction-sadc.com/b2gold-reports-strong-gold-production-for-q1-2022-with-total-gold-production-of-209365-oz-5-above-budget-on-track-to-meet-annual-guidance-of-990000-to-1050000-oz-of-total-gold-production/?share=x)

### Like this:

Like Loading…

### _Related_